Commercial Solar Permits in Los Angeles: Plan Check, Inspections and Utility Approval
How a commercial solar permit works in Los Angeles: LADBS or LA County plan check, fire review, inspections, and LADWP or SCE interconnection before you turn on.
Short answer
A commercial solar permit in Los Angeles runs on two tracks at once: a building and electrical permit from the city or county where the property sits, and an interconnection approval from the utility that serves it. You need both before the system can legally turn on. In the City of Los Angeles that usually means LADBS plan check, Fire Department review and LADWP interconnection. Elsewhere in the county it may mean LA County Building and Safety or another city's building department, plus SCE or a municipal utility. This guide walks through who reviews what, what goes into each submittal and where projects commonly stall.

On this page
It's general information drawn from the agencies' own published material, not a promise about any project's timeline.
Why commercial solar permitting is different from residential
California law treats solar as a matter of statewide concern. Government Code 65850.5 requires cities and counties to approve solar through a building permit or similar nondiscretionary permit, with review limited to health and safety rather than aesthetics.
The fast lanes, though, are built for homes. In the City of LA, LADBS issues online or counter permits only for small rooftop systems on one- or two-family dwellings (subject to size and other conditions). Commercial systems generally go to Regular Plan Check, with a complete plan set under Section 93.0207 of the Los Angeles Electrical Code.
Track 1: the building and electrical permit
Which agency reviews your project
- City of Los Angeles (including the San Fernando Valley neighborhoods inside city limits such as Sylmar, Van Nuys, Chatsworth and Sun Valley): the Los Angeles Department of Building and Safety (LADBS).
- Unincorporated LA County: LA County Public Works, Building and Safety. The county says all solar PV systems require plan check, and unincorporated-area projects are submitted online through EPIC-LA.
- County contract cities: also LA County Building and Safety, submitted through the county's BSOP web application.
- Other incorporated cities (for example San Fernando, Burbank, Glendale or Santa Clarita) run their own building departments with their own submittal rules.
What LADBS looks at
According to LADBS Information Bulletin P/GI 2023-027:
- Building permit for the structure. A building permit is required for the structural support of solar systems. There's a narrow exemption for light, low-profile roof-mounted arrays that meet every one of a list of conditions (weight per square foot, height above the roof, support spacing, a single roofing layer, no overhang and coverage of no more than half the roof). Carports and ground mounts aren't roof-mounted, so they don't fit that exemption.
- Structural plans. Plans show the roof and module layout, the anchors and attachment method, how roof penetrations are sealed, and structural calculations, including wind loads.
- Electrical permit. An electrical permit is required for every PV system, even when the building permit is exempt.
- Listed equipment. PV equipment must be tested and listed by a testing laboratory the City recognizes.
- Fire Department approval. For anything other than a qualifying one- or two-family rooftop system, LAFD approval is required before LADBS issues the electrical permit.
- Historic buildings. Owners must sign an advisory notice before solar goes on a historic building.
What LA County looks at
The county's published steps for solar plan check are: screen the package for completeness, review, corrections, recheck and approval, then permit issuance. For non-residential and ground-mounted projects, the plan checker also issues an agency referral sheet listing other agencies (county, state, federal or others) whose approvals you need before the permit can be issued. The county's roof-mount application also explains how long a plan check approval stays valid and when renewal applies.
Track 2: utility interconnection
The building permit lets you build. The utility's Permission to Operate (PTO) lets you turn the system on. Which utility you deal with depends on the property, not the city name on the mailing address. Our LADWP vs SCE solar guide explains how to check.
LADWP (City of Los Angeles)
LADWP sorts projects by size and complexity. Per its interconnection page:
- Type 3 covers mid-size systems, larger three-phase services and large multi-meter properties such as apartment buildings. Many commercial rooftops and carports land here.
- Type 4 covers the largest projects.
LADWP's page lists the exact size thresholds for each type.
For Type 3, the published steps include an online application with documents and photos (alongside the LADBS permit application), a Work Request number and expenditure recovery charges, engineering review, a pre-construction meeting and "OK to build," a Standard Offer Interconnection Agreement, LADWP final inspection plus the LADBS final, meter installation, and then the PTO notice.
LADWP's engineering submittal list includes a plot plan, a Service Planning Information Form, a one-line diagram, photos of the existing main service and meters, and a battery technical data form when storage is part of the project.
SCE (much of the rest of LA County)
SCE interconnects customer generation under Rule 21. An application package includes a single-line drawing and a site plan. SCE validates the technical data, completes the technical review and issues an interconnection agreement. Once the application is complete and reviewed, SCE issues PTO. For larger or more complex sites, Rule 21 also offers an optional pre-application report; see SCE's Rule 21 page for current details.
Where commercial solar permits commonly slow down
We can't promise timelines, because review times depend on each agency's workload and the project. These are the issues that most often add a round of corrections:
- Incomplete plan sets. Missing structural calcs, roof plans or one-line details send plans back for correction.
- Old electrical gear. Older switchgear or a service that's near capacity can trigger extra engineering on both the permit and the utility side.
- Roof condition. If the roof needs work, sequencing the reroof before the array avoids pulling the system later.
- Extra agency approvals. Fire, historic and other referral agencies each add a review step.
- Utility upgrades. Interconnection review may identify service or transformer upgrades.
- Carports. Canopies are structures with foundations, so they carry more structural review than a flush-mounted roof array. See our solar carports page.
Why permitting timing matters right now
Eligible commercial projects may qualify for the up to 30% federal tax credit (6% base; 30% if prevailing wage and apprenticeship rules are met; eligibility varies, consult a tax advisor). Projects must be placed in service by Dec 31, 2027. Subject to eligibility. Plan check and interconnection both happen before a system is placed in service, so they belong in the schedule from day one. Our commercial solar tax credit deadline post has more background.
Get a free site assessment or call (888) 899-9484.
Frequently asked questions
Do I need a permit for commercial solar in Los Angeles?
Yes. LADBS requires an electrical permit for every PV system and a building permit for the structure unless a narrow roof-mount exemption applies. LA County says all solar PV systems in its jurisdiction require plan check.
Who approves commercial solar in the City of Los Angeles?
LADBS issues the building and electrical permits, LAFD reviews non-residential rooftop systems before the electrical permit is issued, and LADWP handles interconnection and issues Permission to Operate.
What is Permission to Operate?
It's the utility's written approval to turn the system on. LADWP issues a PTO notice after its final inspection and meter work. SCE issues PTO once your interconnection application is complete and reviewed.
How long does commercial solar permitting take?
It varies by agency, project size and how many correction rounds are needed, so we don't quote a standard timeline. A complete plan set and an early utility application are the best ways to avoid delays.
Disclaimer: This article is for general informational purposes only and is not legal, tax, accounting, financial or engineering advice. Tax credits, incentives, utility programs, rates and rules are set by government agencies and utilities, are complex, and can change at any time; eligibility depends on your specific facts. Figures and program details are as published by the cited sources on the date noted and may not be current. Consult your own tax advisor, attorney and other qualified professionals before making decisions. Current Energy does not guarantee eligibility, savings, incentive amounts, approvals or timelines. Nothing in this article is an offer or commitment by Current Energy; any offer or commitment exists only in a written agreement signed by all parties.