The LADWP Feed-in Tariff: How Commercial Property Owners Sell Solar Power to the City

How the LADWP Feed-in Tariff works for commercial property owners: eligibility, 20-year contracts, per-kWh prices, how to apply, and how it differs from NEM.

Short answer

Most commercial solar is built to cut the building's own electric bill. LADWP's Feed-in Tariff (FiT) takes a different approach. Under the FiT, the solar on your roof or parking lot sells all of its output straight to the Los Angeles Department of Water and Power under a long-term contract at a set price per kilowatt-hour. If you own a large roof or lot in the City of Los Angeles and your own power use is modest, that can change how you look at the property. This guide covers how the program works, who qualifies, what's open right now, and how the FiT compares with net metering and with NEM 3.0 in SCE territory.

Aerial view of two solar carport canopies and a rooftop array on a commercial building, installed by Current Energy

What a feed-in tariff is

A feed-in tariff is a standing offer from a utility to buy renewable power from local projects on standard terms. LADWP describes its program as letting property owners and developers "sell the output of local eligible renewable energy projects directly to LADWP (as opposed to consuming the energy onsite to satisfy the customer's load)" (LADWP).

So the FiT array doesn't power your building. It's a separate generator connected to the grid, and your building keeps buying its power from LADWP as it does today. The FiT array earns revenue under a Standard Offer Power Purchase Agreement (SOPPA).

How the LADWP Feed-in Tariff works

Contract term. LADWP buys energy "for a term not exceeding 20 years." You can sign for 20 years, or for 10 years with the option to extend up to 10 more years in one-year increments (LADWP FAQ).

How the price is set. The price is fixed by project size and location, and it covers "all energy, capacity rights, and environmental attributes" from the project. As published by LADWP as of October 2026, prices for solar PV are:

Project capacity In-basin solar PV Owens Valley solar PV
30 kW to 500 kW 14.5¢ per kWh 11.5¢ per kWh
Over 500 kW to 3 MW 14.0¢ per kWh Not available
Over 3 MW 13.5¢ per kWh Not available

Source: LADWP FiT pricing table. Non-PV renewable projects have lower prices on the same page.

Carports and canopies. New qualifying carports and canopies can add a one-time Carport and Canopy Incentive, paid per watt. It's higher in disadvantaged communities and steps down as the project gets bigger (for example, $1.70/W in disadvantaged communities and $1.50/W elsewhere for projects under 500 kW). Projects that take this incentive come with EV-charger requirements. We cover those in solar carports with EV charging.

Program size and capacity. As published by LADWP as of October 2026, the program totals 235 MW, and LADWP lists 127.7 MW in service, 49.1 MW active and 58.2 MW available as of October 7, 2026 (LADWP). The September 2026 dashboard counts 174 projects in service and 102 reserved (dashboard PDF).

Who is eligible

According to LADWP, applicants must:

  • complete the application and supplementary forms;
  • pay the required fees and deposits;
  • have at least one development team member who has built one or more similar projects in LADWP or Southern California Edison territory;
  • show site control over the proposed site; and
  • locate the project inside LADWP's service territory.

The pricing table starts at 30 kW, which is in practice the smallest project size. That puts the FiT in the commercial and industrial range: warehouses, flex buildings, office parks, retail centers and big parking lots. Facilities also need to fit under LADWP's Master Conditional Use Permit or get their own CUP from City Planning. LADWP links to the permit documents from the program page.

Not sure whether you're on LADWP? Our LADWP vs SCE solar guide explains how to check, and our commercial solar in Los Angeles page covers the LADWP-specific paths.

Is it open now, and how do you apply?

Yes. As of October 2026, the standard FiT is accepting applications on a first-come, first-served basis, with 58.2 MW listed as available as published by LADWP as of October 2026. If capacity runs out, new applications go on a waitlist, and LADWP "makes no guarantees if or when more capacity will become available."

What the application involves, per LADWP:

  1. Optional feasibility study. A Stand-Alone Integration Study reports the voltage, service type, hosting capacity and approximate line extension at your site before you apply. The fee is $1,000 up to 500 kW, $2,000 above 500 kW up to 3 MW, and $3,250 above 3 MW.
  2. Hard-copy application. The FiT accepts printed packages only, mailed to LADWP Feed-in Tariff Program, 111 N. Hope St, Room L-43, Los Angeles, CA 90012. An incomplete application doesn't reserve capacity.
  3. Fees and deposit. Expect an application fee, an integration study fee and a $1,500 interconnection study fee. After that study you're billed 10 percent of the interconnection cost, and before the contract is signed you post a Development Security Deposit of $50/kW (CEC-AC), which is refundable once milestones are met.
  4. Contract execution. You sign the SOPPA plus an Interconnection Agreement and LADWP's supplier forms.

LADWP's FiT team can be reached at FiT@ladwp.com.

FiT+: solar plus storage, by competitive bid

LADWP also runs the FiT+ Pilot for paired solar and storage projects in the City of Los Angeles. FiT+ doesn't use a fixed price list. Projects compete by bid for up to 35 MW across three tranches under a 20-year Competitive Offer PPA. A new Tranche A window opened October 12, 2026 and closes January 10, 2027, and it's limited to eligible circuits (LADWP FiT+). According to the FiT+ guidelines, projects must reach commercial operation within 12 months of the contract (one extension may be granted at LADWP's discretion), and part of the interconnection costs can be reimbursed after operation begins.

Feed-in tariff vs net metering vs NEM 3.0

LADWP Feed-in Tariff LADWP net metering SCE Solar Billing Plan ("NEM 3.0")
Where the power goes All sold to LADWP Serves your building first; excess exported Serves your building first; excess exported
What you earn Fixed ¢/kWh under a SOPPA of up to 20 years Bill credits at your rate schedule's energy pricing Hourly export credits that vary by time of day
Size Pricing starts at 30 kW Customer-owned systems up to 1 MW Sized to on-site use
Best fit Big roof or lot, modest on-site use Buildings with meaningful daytime load SCE customers

With LADWP net metering, your system offsets your own usage, and exports are credited at your rate schedule's energy pricing (LADWP). In SCE territory, new solar customers are on the Solar Billing Plan, where exports earn hourly credits based on what the power is worth to the grid at that hour (SCE).

The FiT is the one path where on-site load doesn't drive the design. The size of your roof or lot, plus LADWP's interconnection capacity, sets the system size. For a closer look at feed-in tariff vs net metering under LADWP’s rules, see our comparison.

Is there an SCE equivalent?

Not really for most property owners. SCE's statewide feed-in program is Re-MAT (Renewable Market Adjusting Tariff), set up under Public Utilities Code Section 399.20. SCE reopened it on February 11, 2021, and it reviews requests on a rolling, first-come, first-served basis through its Re-MAT portal (SCE). Re-MAT is for small RPS-eligible generators of 3 MW or less (CPUC), and it's open only to Qualifying Facility sellers.

Re-MAT prices are reset each year by the CPUC. For 2026, Resolution E-5457 sets $67.40/MWh for the As-Available Peaking category (where solar falls), which works out to about 6.7¢ per kWh. As of February 2026, the three investor-owned utilities had signed 65 Re-MAT contracts in total since the program began. The CPUC says Re-MAT replaced the original state feed-in program in 2013. For an SCE building, the usual path is a system sized to on-site load under the Solar Billing Plan.

Fix the roof before you sign a 20-year contract

A FiT contract can last up to 20 years, so the roof underneath it has to last that long too. If the roof gives out partway through, the array comes off, the system stops producing and stops earning, and everyone pays for the removal and reinstallation. The right order is to get an honest assessment of roof condition first. If the roof is near the end of its life, replace it before the array goes on.

One possible structure that may be available for some qualifying projects is a developer-funded arrangement: a developer finances and owns the system, sells the output to LADWP under the FiT, and shares a portion of the program revenue with the property owner. In some cases, roof work may be included in the project scope. Any such arrangement is subject to site evaluation, LADWP program acceptance and available capacity, and a written agreement, and terms vary by project. Before committing, ask any installer or developer to spell out in writing who owns the system, who pays for which costs, who holds the SOPPA, and how revenue is shared.

The federal tax credit and the 2027 deadline

FiT projects may also qualify for federal incentives. The commercial credit is up to 30% federal tax credit (6% base; 30% if prevailing wage and apprenticeship rules are met; eligibility varies, consult a tax advisor). Projects must be placed in service by Dec 31, 2027. Subject to eligibility. Interconnection studies and contract steps have to fit inside that window, so read our commercial solar tax credit deadline guide before planning a schedule.

Talk to a commercial team that knows LADWP

Current Energy has 200+ MW designed, engineered and installed, including Feed-in Tariff work such as our Chatsworth commercial building, with a rooftop array and new carports. Big jobs need specialized skills and resources. We have both. We'll look at your roof or lot, your utility and your on-site load, and tell you whether the FiT, net metering or a mix makes more sense. Learn more about our commercial solar services.

Get a free site assessment or call (888) 899-9484.

See the Feed-in Tariff overview and send a roof for review: Rent us your roof.

Frequently asked questions

What is the LADWP Feed-in Tariff?

It's an LADWP program that buys the full output of eligible local renewable projects under a Standard Offer Power Purchase Agreement of up to 20 years, at a set price per kWh based on project size and location.

How big does a project have to be?

LADWP's pricing table starts at 30 kW, and prices step down for projects over 500 kW and over 3 MW. The project has to be in LADWP's service territory.

Is the LADWP FiT open right now?

Yes, as published by LADWP as of October 2026: LADWP lists 58.2 MW of capacity available, assigned first come, first served. When capacity is full, applications go on a waitlist. The separate FiT+ solar-plus-storage window runs from October 12, 2026 to January 10, 2027.

Can I use FiT power in my own building?

No. Standard FiT output is sold to LADWP and isn't used on site. If you want to offset your own bill, look at LADWP net metering. FiT+ allows on-site use only in its resiliency and peak-shaving operating modes.

Disclaimer: This article is for general informational purposes only and is not legal, tax, accounting, financial or engineering advice. Tax credits, incentives, utility programs, rates and rules are set by government agencies and utilities, are complex, and can change at any time; eligibility depends on your specific facts. Figures and program details are as published by the cited sources on the date noted and may not be current. Consult your own tax advisor, attorney and other qualified professionals before making decisions. Current Energy does not guarantee eligibility, savings, incentive amounts, approvals or timelines. Nothing in this article is an offer or commitment by Current Energy; any offer or commitment exists only in a written agreement signed by all parties.

Talk to a commercial team that knows LADWP

We’ll look at your roof or lot, your utility and your on-site load, and tell you whether the FiT, net metering or a mix makes more sense.

Get a free consultation

Solar, battery storage, EV charging, lighting, HVAC and more. Tell us about your project.

Services of interest (tick all that apply)
Preferred contact method *

Optional. We still reply if you leave this unticked — consent to be texted is never required to get a quote.

No cost, no obligation.

Call now Free assessment